How Household Electric Bills Are Paying $9.3 Billion for Data Center Power Plants

Period covered: 2024 to 2025 · 11 sources

Summary

The cost of generating capacity in PJM, the market that serves 65 million people in 13 states, went from $2.2 billion to $14.7 billion in one auction, and the market's independent monitor attributed $9.3 billion of that to data center load. In Louisiana and Virginia, utilities are building gas plants for Meta and for data centers under contracts the public cannot read. Maryland and Oregon passed laws in 2025 to put data centers in a rate class of their own.

Cassandra Lainez lives in northern New Jersey and reads her electric bill. In July 2025 her usage was down from the year before and the bill was up, $29 more in the box marked supply charges. She asked a neighbor, who did not know where to find her bill, and when they found it the supply section had gone up the same way. More Perfect Union started there and went 300 miles south to find out why.

The auction

The price a utility pays for power is set in regional markets, and the largest is PJM, which coordinates the grid for about 65 million people from Illinois to Washington. Once a year PJM holds a capacity auction in which generators are paid to be available three years out. In the auction held in July 2024, for the 2025 to 2026 delivery year, the price cleared at $269.92 per megawatt day, from $28.92 the year before, and the total went from $2.2 billion to $14.7 billion. David Lapp, who represents residential ratepayers in Maryland as the state's people's counsel, told More Perfect Union the prices went up by about 800 percent and that utilities pass the capacity price on as supply charges. PJM's independent market monitor, Monitoring Analytics, found that data center load accounted for $9.3 billion of the auction's cost, which is 63 percent. The next auction, held July 22, 2025, cleared at the price cap of $329.17 and cost $16.1 billion, and the monitor's analysis of it found that the 11,993 megawatts of existing and forecast data center load in PJM's forecast raised the cost by $7.3 billion. The one after that, in December 2025, cleared at the new cap of $333.44 and cost $16.4 billion, and came in 6,500 megawatts short of the reserve PJM says it needs.

Data centers were about 4 percent of American electricity demand when the video was made and expected to triple within three years. Tyson Slocum of Public Citizen said the country has never generated more electricity than it does now, and that demand is bursting through the envelope almost entirely because of data centers. Julie Bolthouse, who researches the industry's growth in northern Virginia, said Loudoun County alone has more than 200 data centers built or approved and is the largest data center market in the world. In 2025 the industry expected to spend about $475 billion on data centers, 42 percent more than the year before.

The plants

Higher prices are one cost. The other is the new plants and lines, which under the utility business model are paid for by every customer, plus a regulated profit for the utility of about 10 percent. Ari Peskoe, who runs the Electricity Law Initiative at Harvard Law School, and his colleague Eliza Martin reviewed nearly 50 regulatory proceedings around the country for a paper published March 5, 2025. They found that the deals between utilities and data centers are typically hidden from the public, behind nondisclosure agreements and blacked out filings, and that when a data center underpays for the infrastructure built for it, the shortfall goes to everyone else. Utilities have a reason to make those deals: a data center is a reason to build, and building is how a utility earns.

Louisiana is the example the video uses. Entergy Louisiana proposed three gas plants at $3.2 billion to serve Meta's data center in Richland Parish, with Meta on a 15 year contract. The full terms are secret. From the redacted filings, Peskoe's reading was that Meta is obligated to pay for about half of the $3 billion to $4 billion of infrastructure, and the rest is at risk of landing on the state's other customers. The Louisiana Public Service Commission approved the plants on August 20, 2025 by a vote of 4 to 1, with a $550 million transmission line that Entergy said would not be needed without the data center.

Virginia is the other. Dominion Energy's long range plan, filed October 22, 2025, calls for six new gas plants and projects the typical residential bill at $308 a month in 2035 and $381 in 2045. The video cites an earlier Dominion projection that residential bills would more than double to $315 a month within 15 years, mostly because of data centers, at a time when residential demand has not grown. On November 25, 2025 the State Corporation Commission approved the first of the plants, a 944 megawatt gas plant in Chesterfield County at $1.47 billion, and residential increases of $11.24 a month in January 2026 and $2.36 more in January 2027. The same order created a separate rate class for customers over 25 megawatts, which covers most data centers, with 14 year contracts and minimum charges whether or not the power is used.

The laws

That separate class is what the advocates in the video asked for. Maryland's Next Generation Energy Act, signed May 20, 2025, orders the state's utilities to create stand alone tariffs for data centers and other large loads so that what is built for them can be charged to them. Oregon's POWER Act, House Bill 3546, signed June 16, 2025, requires a separate rate classification for facilities over 20 megawatts, with contracts that commit them to the costs. Lapp called Maryland's law an important first step, and said the industry says it welcomes paying its costs but does not advocate for reforms that would make it.

The Data Center Coalition, whose members include Amazon, Meta, Google, and Microsoft, opposes these bills at state capitals. The video says its Virginia PAC gave more than $2 million to state legislators in 2024, and that several data center bills were voted down in the 2025 session. The Virginia Public Access Project lists $640,100 raised by the coalition's committee since 2024, with the largest gifts from STACK Infrastructure, Cloud HQ, Vantage, and Amazon. The coalition's position is that its members already pay their fair share. Slocum's is that the numbers do not lie.

← 2020 to today

Primary Sources (11)

Documents, court filings, official reports, and broadcasts cited in this report.

Virginia Public Access Project. Contributions to the coalition's Virginia committee since 2024.
More Perfect Union. Reporting from northern Virginia with Ari Peskoe, Tyson Slocum, David Lapp, and Julie Bolthouse on who pays for the buildout.
2025
Harvard Law School Electricity Law Initiative. Eliza Martin and Ari Peskoe's review of nearly 50 regulatory proceedings on utility deals with data centers.
2025
Maryland General Assembly. Signed May 20, 2025. Orders stand alone tariffs for data centers and other large loads.
2025
Oregon Legislature. Requires a separate rate classification and contracts for large energy use facilities.
2025
PJM Interconnection. The auction that cleared at the $329.17 cap. PJM's results release the same day gives the comparison to $269.92 the year before.
2025
The Lens. The Louisiana Public Service Commission's 4 to 1 vote on August 20, 2025.
2025
Monitoring Analytics, PJM Independent Market Monitor. The market monitor's attribution of auction costs to data center load: $9.33 billion of the 2025/2026 auction and $7.27 billion of the 2026/2027 auction.
2025
Virginia Mercury. Dominion's 2025 resource plan update: six gas plants and residential bills of $308 a month in 2035 and $381 in 2045.
2025
Virginia Mercury. The 944 megawatt plant at $1.47 billion, the residential increases, and the rate class for customers over 25 megawatts.
2025
PJM Interconnection. Cleared at the $333.44 cap, $16.4 billion total, 6,517 megawatts short of the reliability requirement. Includes the prior auctions' prices and totals: $14.7 billion for 2025/2026 and $16.1 billion for 2026/2027.

Documented Records (9)

Chronological entries extracted from the primary sources above.

2024
July 30, 2024
PJM's capacity auction for the 2025 to 2026 delivery year cleared at $269.92 per megawatt day, from $28.92 the year before, and the total cost went from $2.2 billion to $14.7 billion. PJM coordinates the grid for about 65 million people in 13 states and Washington. The market's independent monitor found that data center load accounted for $9.33 billion of the total, 63 percent. Utilities pass the capacity price to customers in the supply charge on the bill.
PJM Interconnection. Violates: None in law. Listed because every household in the region pays it.. Source: Analysis of the 2026/2027 RPM Base Residual Auction, Part A, Monitoring Analytics, PJM Independent Market Monitor
2025
March 5, 2025
Eliza Martin and Ari Peskoe of the Harvard Electricity Law Initiative reviewed nearly 50 regulatory proceedings and found that the deals between utilities and data centers are typically hidden from the public behind nondisclosure agreements and redacted filings, that utilities have a financial reason to offer discounts because they profit from building, and that when a data center underpays for the infrastructure built for it the shortfall goes to the utility's other customers.
Utilities and data center companies. Violates: None in law. Listed for the mechanism.. Source: Extracting Profits from the Public: How Utility Ratepayers Are Paying for Big Tech's Power, Harvard Law School Electricity Law Initiative
May 20, 2025
Maryland's Next Generation Energy Act, Senate Bill 937, chapter 625, was signed by the governor. Among its provisions it orders the state's utilities to create stand alone tariffs for data centers and other large loads, so that infrastructure built for them can be charged to them instead of to every household.
Maryland General Assembly. Violates: None in law. Listed as the record of a state that acted.. Source: Senate Bill 937, the Next Generation Energy Act (Maryland, chapter 625 of 2025), Maryland General Assembly
June 16, 2025
Oregon's POWER Act, House Bill 3546, chapter 323 of 2025, requires the Public Utility Commission to establish a separate rate classification for large energy use facilities over 20 megawatts and requires utilities to serve them under contracts that commit them to the costs. It passed with an emergency clause and took effect on signing.
Oregon Legislature. Violates: None in law. Listed as the record of a state that acted.. Source: House Bill 3546, the POWER Act (Oregon Laws 2025, chapter 323), Oregon Legislature
July 22, 2025
PJM's auction for the 2026 to 2027 delivery year cleared at the price cap of $329.17 per megawatt day and cost $16.1 billion. PJM said forecast peak load had grown by more than 5,400 megawatts in a year, driven largely by data center expansion. The independent monitor found that including 11,993 megawatts of existing and forecast data center load in the forecast raised the auction's cost by $7.27 billion, an 82 percent increase over what it would have been without them.
PJM Interconnection. Violates: None in law. Listed for the number.. Source: 2026/2027 Base Residual Auction Report, PJM Interconnection
2024 to 2025
More Perfect Union's account: a New Jersey customer whose usage fell and whose supply charge rose $29; Loudoun County with more than 200 data centers built or approved; the industry spending about $475 billion on data centers in 2025; data centers at about 4 percent of national demand and expected to triple in three years; and estimates that data centers will add $160 billion to grid costs over 15 years and that household rates could rise as much as 70 percent. The Data Center Coalition's position is that its members already pay their fair share.
“Meta has signed a 15-year deal and it only obligates them to pay for about half of that $3 to $4 billion of infrastructure, which means that there's a big risk that everyone else in Louisiana will get stuck with the rest of that bill.”
More Perfect Union. Violates: None in law. The figures are the video's; the auction numbers are PJM's and the monitor's.. Source: We Found the Hidden Cost of Data Centers. It's in Your Electric Bill, More Perfect Union
August 20, 2025
The Louisiana Public Service Commission voted 4 to 1 to approve three Entergy gas plants, 2,262 megawatts at $3.2 billion, to serve Meta's data center in Richland Parish, plus a $550 million transmission line Entergy said would not be needed without it. Meta's contract runs 15 years and its full terms are sealed; the plants are built to run 30 years or more. Commissioner Davante Lewis voted no. Commissioner Foster Campbell said he was one thousand percent for it.
Louisiana Public Service Commission; Entergy Louisiana; Meta. Violates: None in law. Listed because the state's other customers carry whatever the sealed contract does not.. Source: Entergy gets green light for three controversial new gas plants to power Meta data center, The Lens
November 25, 2025
Virginia's State Corporation Commission approved Dominion Energy's 944 megawatt gas plant in Chesterfield County at $1.47 billion and residential increases of $11.24 a month in January 2026 and $2.36 more in January 2027. The same order created a rate class for customers over 25 megawatts, covering most data centers, with 14 year contracts and minimum charges of 85 percent for transmission and distribution and 60 percent for generation whether or not the power is used. Dominion's plan filed October 22, 2025 calls for six new gas plants and projects the typical residential bill at $308 a month in 2035 and $381 in 2045.
Virginia State Corporation Commission; Dominion Energy. Violates: None in law. Listed for what the residential bill is projected to become.. Source: SCC approves Chesterfield gas plant and Dominion rate hike, creates new rate class for data centers, Virginia Mercury
December 17, 2025
PJM's auction for the 2027 to 2028 delivery year cleared at the new cap of $333.44 per megawatt day, cost $16.4 billion, and procured 6,517 megawatts less than the reliability requirement, a 14.4 percent reserve margin against a 20 percent target. The requirement had risen by 5,250 megawatts in a year, which PJM attributed largely to additional large loads.
PJM Interconnection. Violates: None in law. Listed for the number and the shortfall.. Source: 2027/2028 Base Residual Auction Report, PJM Interconnection

Timeline Events (6)

Dated events from this investigation in the site timeline.

November 25, 2025
Virginia approves Dominion's Chesterfield gas plant and a rate class for data centers
944 megawatts at $1.47 billion; residential bills up $11.24 a month in January 2026.
July 22, 2025
PJM auction clears at the price cap, $16.1 billion
$329.17 per megawatt day. The monitor found data center load added $7.27 billion.
June 16, 2025
Oregon's POWER Act signed
House Bill 3546 requires a separate rate class and contracts for facilities over 20 megawatts.
May 20, 2025
Maryland orders separate tariffs for data centers
The Next Generation Energy Act, chapter 625, signed by the governor.
March 5, 2025
Harvard review finds utility deals with data centers hidden from the public
Nearly 50 proceedings reviewed. When a data center underpays for what is built for it, the rest of the customers cover the difference.
July 30, 2024
PJM capacity auction rises from $2.2 billion to $14.7 billion
The price cleared at $269.92 per megawatt day, from $28.92. The market monitor attributed $9.3 billion of the total to data center load.