Project Blue: The Secret Amazon Data Center Deal Rejected by Tucson Voters

Period covered: June to December 2025 · 6 sources

Summary

Officials in Tucson and Pima County signed nondisclosure agreements about a 290 acre data center campus known only as Project Blue. Public records tied it to Amazon. It would have used 1,910 acre feet of water a year, about 6 percent of the city's supply, in a drought. On August 6, 2025 the city council voted unanimously to end the negotiations. The developer kept the county's land and got its power contract approved in December.

The project came to Tucson under a code name. City and county officials signed nondisclosure agreements with the developer, Beale Infrastructure, and the public was told about Project Blue: a $3.6 billion data center campus on 290 acres of county land near the fairgrounds southeast of the city, 180 permanent jobs, and a request to be annexed into Tucson so it could be connected to city water. A document obtained through a public records request identified the company behind it as Amazon Web Services. Amazon's statement was that it had done due diligence and had no commitments or agreements.

The water

Tucson is in the Sonoran Desert and had been under drought restrictions. Project Blue would have used 1,910 acre feet of water a year at full build out, about 6 percent of the city's supply, and it would have used drinking water for at least the first two years, until a reclaimed water pipeline was finished. The developer's answer was that the project would be net water positive over time, through paying for turf removal, water saving appliances in homes, and treatment of wells contaminated with PFAS. The proposal submitted to the county did not include an estimate of daily water use.

In June 2025 the Pima County Board of Supervisors voted 3 to 2 to sell the 290 acres to the developer. That put the decision on annexation and water in front of the Tucson City Council. Residents filled the meetings. On August 6, 2025 the council voted unanimously to end negotiations and take the annexation and development agreement off its agenda. The Ward 4 member said the way data centers are being built is not sustainable and not the development her residents want. The Ward 1 member said Tucson needed to be the city that says not here, not now, and not like this. The mayor said it was her responsibility to create guardrails to protect the city from an industry that is already in Arizona. The council then moved to write rules for large water users and zoning requirements for data centers.

What happened after

The council's vote ended the city's part. It did not end the project. The county's land sale and zoning approvals stood, and Beale Infrastructure went ahead on the county land outside the city limits, without Tucson water. It switched the design from water cooling to air cooling, which reduced the computing capacity to fit the power already allocated by Tucson Electric Power. In December 2025 the Arizona Corporation Commission approved the power sale agreement between the project and TEP by a vote of 4 to 1, with the dissenting commissioner asking whether ratepayers were adequately protected. The developer would not name an operator, saying only that it would have one by the time the buildings come online in 2027. Reporting indicated Amazon had withdrawn after the change to air cooling; the project has never confirmed Amazon's involvement or its departure. In September 2025 the county board changed its own rules to limit the length and scope of NDAs it will sign.

← 2020 to today

Primary Sources (6)

Documents, court filings, official reports, and broadcasts cited in this report.

Vanessa Wingårdh. Electric bills, the PJM auction, the tax exemptions in Louisiana, Virginia, and Texas, Morrow County, Tucson, and Memphis.
2025
Arizona Center for Investigative Reporting. The 3 to 2 county vote in June 2025 and the missing water estimate.
2025
Arizona Luminaria. The unanimous vote and the council members' statements.
2025
KJZZ. The 1,910 acre feet a year figure, the drinking water in the first two years, and the Amazon records.
2025
KJZZ. The Arizona Corporation Commission's 4 to 1 approval of the power agreement and the switch to air cooling.
2026
Governing. The ten states with bills to restrict NDAs and Pima County's new limits on them.

Documented Records (2)

Chronological entries extracted from the primary sources above.

2025
June to December 2025
Tucson and Pima County officials signed nondisclosure agreements about Project Blue, a 290 acre data center campus that public records tied to Amazon Web Services. It would have used 1,910 acre feet of water a year, about 6 percent of the city's supply, with drinking water for the first two years. The county sold the land in June 2025 by a 3 to 2 vote. On August 6, 2025 the Tucson City Council voted unanimously to end negotiations. The developer went ahead on the county land with air cooling, and in December 2025 the Arizona Corporation Commission approved its power contract 4 to 1.
“We need to be the city that says not here, not now and not like this.”
Pima County Board of Supervisors; Tucson City Council; Beale Infrastructure. Violates: None in law. Listed as the record of a community that refused and what happened next.. Source: Tucson City Council rejects Project Blue data center amid intense community pressure, Arizona Luminaria
August 2025
Vanessa Wingårdh's account: electric bills of $327, $370, and $600 to $800 shown by the people paying them; Virginia's exemption at $730 million; $29 billion in rate increases approved in the first half of 2025; six technology companies reporting $61.5 million in lobbying with 300 lobbyists; $1.9 billion in untraceable money in the 2024 election; Memphis rates up 4 percent a year for three years; and San Antonio data centers using 463 million gallons of water in two years of drought.
“When local officials celebrate landing a data center with massive tax breaks, what they're really saying is, we increased your taxes to subsidize a trillion dollar company.”
Vanessa Wingårdh. Violates: None in law. The figures are the video's; the auction, exemption, abatement, ethics, and permit records are cited separately.. Source: The Real Reason Your Power Bill Doubled (It's Not Inflation), Vanessa Wingårdh

Timeline Events (1)

Dated events from this investigation in the site timeline.

August 6, 2025
Tucson City Council votes unanimously against Project Blue
The 290 acre campus tied to Amazon would have used about 6 percent of the city's water. The developer went ahead on county land.