2020 to today · Energy, Utilities & Data Centers

Meta's $50 Billion Louisiana Data Center: Shell Companies, $3.3 Billion in Tax Breaks, and 10 Gas Plants

Period covered: 2024 to 2026 · 9 sources

Summary

The company applied for a water permit in Richland Parish as Leley LLC, for a project called Sucre. Its sales tax exemption was approved in July 2024 without a public estimate of its value; a later estimate is $3.3 billion. In August 2025 the Public Service Commission approved three gas plants at $3.2 billion, with Meta committed for 15 years and the plants built to run for 30 or more. In July 2026 the project grew to 5 gigawatts and $50 billion, with seven more gas plants.

Richland Parish is in the flatlands of northeast Louisiana, a place of soybean fields and river cane. In November 2024 a newly created Delaware company, Leley LLC, applied to the state for a water quality certification for a project called Sucre. The company was Meta. In July 2024 state officials had already approved a sales tax exemption for the project, still under its code name, under a law the legislature had passed quickly earlier that year, and without a public estimate of what the exemption would cost. In January 2025 Meta announced Hyperion: a $10 billion data center on 2,250 acres, 4 million square feet, two gigawatts and more, to train future versions of its Llama models. Governor Jeff Landry's statement said the investment establishes the region as an anchor in Louisiana's rapidly expanding tech sector, revitalizes one of the state's beautiful rural areas, and creates opportunities for Louisiana workers to fill high paying jobs of the future, and thanked Meta for its commitment to the state.

A resident of Holly Ridge, the unincorporated community next to the site, told Erin Brockovich she found out about it the way everyone else in her community did, when they started digging.

The exemption

The value of the sales tax exemption was not published. Early reporting put the exemption at upwards of $1 billion. In May 2026 a reporter at Sherwood News estimated $3.3 billion by applying Louisiana's combined state and local sales tax rate of 9.56 percent to the roughly $35 billion in chips Meta is expected to buy for the site over the 20 year exemption. The land itself is leased at $732,000 a year with an option to buy for $12 million. Meta's own figures for permanent employment were 300 to 500 operational roles, with more than 5,000 construction workers at the peak. A regional analysis projected about 326 direct local jobs. The governor's answer to the question of whether it was 500 jobs or five was that he would take it, that five jobs in that area was a big thing before this came, and that Jesus started with twelve.

The plants

Entergy Louisiana asked the Public Service Commission to approve three new gas plants, 2,262 megawatts, at a cost of $3.2 billion, plus a $550 million transmission line the company acknowledged would not be needed without the data center. The full terms of Meta's contract are confidential. From the redacted filings, Ari Peskoe of the Harvard Electricity Law Initiative read Meta's obligation as covering about half of the $3 billion to $4 billion of infrastructure over a 15 year contract, with the rest at risk of falling on Entergy's other customers. The plants are built to run for 30 or 40 years. Louisiana ratepayers will pay for fuel, operations, and the line. Entergy's estimate of the effect on a residential bill was about a dollar, and the Union of Concerned Scientists estimated the deal would produce about $178 million a year in new profit for Entergy's shareholders.

On August 20, 2025 the commission approved the plants by a vote of 4 to 1. Commissioner Davante Lewis voted no. Commissioner Foster Campbell said he was one thousand percent for the deal and that the data center is to north Louisiana what the Superdome is to New Orleans.

The data center will use, by one measure, more electricity than the city of New Orleans, and by another, three times what New Orleans uses in a year. In April 2026 the commission voted 4 to 1 to put an expansion on a fast track: seven more gas plants, three grid scale batteries, about 240 miles of new transmission line, and increases at the state's nuclear plants, with a decision expected in December 2026. On July 13, 2026 Meta announced the campus would grow to 5 gigawatts, with an investment of up to $50 billion, $1 billion for local roads, water, and sewer, and about 1,000 local jobs once it is running. The governor said projects like this ensure America continues to lead.

The pattern in the state

Since Governor Landry took office in January 2024, elected officials in Louisiana have signed at least 54 nondisclosure agreements on data center projects. On one project in Boyce, which went by Project Lightning and then Project Pixel before it was announced as a $3.6 billion campus, the signers included at least five state senators, the parish assessor, and the members of the industrial development board. The board's executive director told a town hall that NDAs are not illegal and that nobody was going to change his mind about them. In West Feliciana Parish, the parish president took a $10 billion data center without signing one and posted the information on the parish website.

← 2020 to today

Primary Sources (9)

Documents, court filings, official reports, and broadcasts cited in this report.

Theo Von Clips. Erin Brockovich on the nondisclosure agreements, the Tyrone Township clip, the Spartanburg lawsuit, and Microsoft's announcement.
The Brockovich Report. Erin Brockovich's essay: the map, 3,862 reports in a month, the Holly Ridge resident, and Governor Landry's statement.
Vanessa Wingårdh. Electric bills, the PJM auction, the tax exemptions in Louisiana, Virginia, and Texas, Morrow County, Tucson, and Memphis.
More Perfect Union. Reporting from northern Virginia with Ari Peskoe, Tyson Slocum, David Lapp, and Julie Bolthouse on who pays for the buildout.
2025
The Lens. The Louisiana Public Service Commission's 4 to 1 vote on August 20, 2025.
2025
Union of Concerned Scientists. The 15 year contract against a 30 to 40 year plant life, the $550 million line, and the estimate of new shareholder profit.
2026
Moneywise, via Yahoo Finance. The Sherwood News estimate of the sales tax exemption, the land lease, the job figures, and the Project Sucre code name.
2026
Data Center Dynamics. The July 2026 expansion: seven more gas plants, three batteries, 240 miles of line.
2026
NPR, Gulf States Newsroom. At least 54 NDAs signed by Louisiana officials since 2024, the Boyce project, the Virginia survey, and the Pennsylvania order.

Documented Records (7)

Chronological entries extracted from the primary sources above.

2025
2024 to 2025
More Perfect Union's account: a New Jersey customer whose usage fell and whose supply charge rose $29; Loudoun County with more than 200 data centers built or approved; the industry spending about $475 billion on data centers in 2025; data centers at about 4 percent of national demand and expected to triple in three years; and estimates that data centers will add $160 billion to grid costs over 15 years and that household rates could rise as much as 70 percent. The Data Center Coalition's position is that its members already pay their fair share.
“Meta has signed a 15-year deal and it only obligates them to pay for about half of that $3 to $4 billion of infrastructure, which means that there's a big risk that everyone else in Louisiana will get stuck with the rest of that bill.”
More Perfect Union. Violates: None in law. The figures are the video's; the auction numbers are PJM's and the monitor's.. Source: We Found the Hidden Cost of Data Centers. It's in Your Electric Bill, More Perfect Union
August 2025
Vanessa Wingårdh's account: electric bills of $327, $370, and $600 to $800 shown by the people paying them; Virginia's exemption at $730 million; $29 billion in rate increases approved in the first half of 2025; six technology companies reporting $61.5 million in lobbying with 300 lobbyists; $1.9 billion in untraceable money in the 2024 election; Memphis rates up 4 percent a year for three years; and San Antonio data centers using 463 million gallons of water in two years of drought.
“When local officials celebrate landing a data center with massive tax breaks, what they're really saying is, we increased your taxes to subsidize a trillion dollar company.”
Vanessa Wingårdh. Violates: None in law. The figures are the video's; the auction, exemption, abatement, ethics, and permit records are cited separately.. Source: The Real Reason Your Power Bill Doubled (It's Not Inflation), Vanessa Wingårdh
August 20, 2025
The Louisiana Public Service Commission voted 4 to 1 to approve three Entergy gas plants, 2,262 megawatts at $3.2 billion, to serve Meta's data center in Richland Parish, plus a $550 million transmission line Entergy said would not be needed without it. Meta's contract runs 15 years and its full terms are sealed; the plants are built to run 30 years or more. Commissioner Davante Lewis voted no. Commissioner Foster Campbell said he was one thousand percent for it.
Louisiana Public Service Commission; Entergy Louisiana; Meta. Violates: None in law. Listed because the state's other customers carry whatever the sealed contract does not.. Source: Entergy gets green light for three controversial new gas plants to power Meta data center, The Lens
2026
July 2024 to May 2026
Meta applied for its Richland Parish water permit in November 2024 as Leley LLC, for a project called Sucre, after its sales tax exemption had been approved in July 2024 with no public estimate of its value. A May 2026 estimate by a Sherwood News reporter put the exemption at $3.3 billion: the 9.56 percent combined sales tax rate on about $35 billion of chips over the 20 year exemption. Meta's own employment figure is 300 to 500 permanent roles; a regional analysis projected about 326.
Meta; State of Louisiana. Violates: None in law. Listed because the exemption was granted before the company's name or the cost was public.. Source: Meta got a $3.3 billion tax break for its $10 billion AI data center in Louisiana, Moneywise, via Yahoo Finance
2026
Erin Brockovich's map at brockovichdatacenter.com received 3,862 reports from residents in its first month, with 2,716 pins in 49 states, and crashed twice in its first 72 hours. The reports described the same sequence: residents not told, council members under nondisclosure agreements, and construction as the first notice. A resident of Holly Ridge, Louisiana, next to Meta's campus, said nobody told them anything.
“Nobody told us anything. They supposedly had a big meeting. The whole community was supposed to come. Nobody knew anything about it. Ever.”
Local governments and data center developers. Violates: None in law. Listed for the pattern.. Source: If Data Centers Are So Great, Why Are They Being Built in Secret?, The Brockovich Report
July 13, 2026
Meta announced that its Richland Parish campus would grow from 2 to 5 gigawatts with an investment of up to $50 billion, seven more gas plants, three grid scale batteries, and about 240 miles of new transmission line to be built by Entergy, after the Public Service Commission voted 4 to 1 in April 2026 to fast track the expansion with a decision expected in December 2026.
Meta; Entergy Louisiana; Louisiana Public Service Commission. Violates: None in law. Listed for scale.. Source: Meta expands data center campus in Richland Parish, Louisiana, to 5GW, will invest $50bn, Data Center Dynamics
January 2024 to August 2026
Elected officials in Louisiana have signed at least 54 nondisclosure agreements on data center projects since Governor Landry took office in January 2024. On a $3.6 billion project in Boyce that went by Project Lightning and Project Pixel, the signers included at least five state senators, the parish assessor, and members of the industrial development board. A 2025 survey found NDAs in at least 25 of 31 Virginia data center projects. In August 2026 the governor of Pennsylvania barred state agencies from signing them, and bills to restrict them were introduced in at least ten states.
“Our politicians were elected to represent us, not to represent industry.”
Louisiana state and parish officials. Violates: None in law. Listed for the count.. Source: NDAs are hiding data center deals, drawing ire from locals and attention from lawmakers, NPR, Gulf States Newsroom

Timeline Events (2)

Dated events from this investigation in the site timeline.

July 13, 2026
Meta's Louisiana campus grows to 5 gigawatts and $50 billion
Seven more gas plants, three batteries, and 240 miles of line, with a commission decision expected in December.
August 20, 2025
Louisiana approves three gas plants for Meta, 4 to 1
2,262 megawatts at $3.2 billion, a 15 year contract with sealed terms, and a $550 million line.
Meta's $50 Billion Louisiana Data Center: Shell Companies, $3.3 Billion in Tax Breaks, and 10 Gas Plants | Spirit of '76