How Cities and Counties Sign Secret NDAs Before Approving Data Centers
Period covered: 2006 to 2026 · 11 sources
Summary
Erin Brockovich put up a map where people could report a data center near them and got 3,862 reports in a month from 49 states. The reports said the same thing: nobody was told, the officials had signed nondisclosure agreements, and the announcement was the construction. Elected officials in Louisiana have signed at least 54 NDAs since 2024. Microsoft ended its use of NDAs with local governments in March 2026.
Erin Brockovich got 30 emails in one morning from one community about the same thing, data centers. After 30 years of this work she treats a cluster of emails as a sign, and she said the moment was like Hinkley, California in the 1990s, when the question was what hexavalent chromium was. She built a map at brockovichdatacenter.com where anyone living near a data center could report what was happening, the way she had built self reporting registries before, because everything else people report goes through an agency. The map crashed twice in the first 72 hours. By the time she wrote about it, 3,862 people had filed reports and the map showed 2,716 pins in 49 states. On the third day, she told Theo Von, she woke up and understood it was not one town and one aquifer. It was the whole country.
What the reports said
The reports from different states described the same sequence. Residents were not told. City council members had signed nondisclosure agreements with the company before the neighbors knew a project was being considered. Many people thought a warehouse or a solar farm was going in. Construction was the first notice, and by then the permits were secured. Brockovich's explanation for the councils is not that they are corrupt but that they are small and underfunded, a company arrives talking about $10 billion, and signing an NDA does not seem like much in exchange for jobs and a tax base that, in her account, mostly do not arrive. Her point about the companies is different. They are the biggest companies in the world, they know what they are doing, and the transparency is theirs to give.
She used the example of Meta's Hyperion campus in Richland Parish, Louisiana, a 4 million square foot facility that will use more electricity than the city of New Orleans and cover a footprint the size of lower Manhattan. Governor Landry's press statement thanked Meta for its commitment to the state. A resident of Holly Ridge, the unincorporated community next to it, told Brockovich she found out the way everyone else did, when they started digging. Nobody told us anything, she said. There was supposedly a big meeting the whole community was supposed to come to, and nobody knew anything about it, ever.
The clip Von played was from Tyrone Township, Michigan, on June 16, 2026. A resident went down the board table asking each member whether they had personally signed any NDA or had any private communication with a developer about a project that could affect the township. Two said no. One said she was not answering and it was not the time or place. Another said it was not the place and they had already discussed it. The rest did not answer, and the resident who followed her was told to stop. The township later posted a statement that no board or commission member has such an NDA and that a public records request for any NDAs was answered with none, and explained that the public comment period is not a question and answer session. Both things are in the record: the officials would not answer a direct question in public, and the township says the answer was no.
Spartanburg
In Spartanburg County, South Carolina, a company called Valara Holdings LLC filed an application to redevelop about 905,000 square feet of the former Kohler plant on South Pine Street as a minor land development. The county approved it. Weeks later the company filed a second application, for four buildings totaling about 494,000 square feet with a power yard, a metering station, mechanical cooling systems, and stormwater ponds, also as a minor development, and the county approved that too. The project is a data center of nearly $3 billion. Under the county's land ordinance a major development requires planning commission review, public meetings, and a documented decision; a minor one does not. On July 6, 2026 a group called Concerned Citizens of Spartanburg County sued the county and the company, asking a court to require the review that a major development gets. The county declined to comment on the litigation.
The playbook is old
The practice goes back to the first large data center. Google's first one opened in The Dalles, Oregon in 2006. The company had negotiated with the city through an entity called Design LLC, received a 15 year property tax exemption, and had local officials sign nondisclosure agreements. When the city expanded the arrangement in 2021, officials had signed an NDA that barred them from saying how much water Google used, the company called the figure a trade secret, and the city sued a newspaper to keep the records closed. After a year the city and Google gave up and the records showed the data center using about a quarter of the city's water. In Louisiana, elected officials have signed at least 54 NDAs on data center projects since Governor Landry took office in 2024, including at least five state senators and a parish assessor on a project in Boyce that went by the names Project Lightning and Project Pixel. In Virginia a researcher found NDAs in at least 25 of 31 data center projects he surveyed. One parish in Louisiana, West Feliciana, took a $10 billion project without an NDA and posted everything on the parish website; its president said they were proud to have done it that way.
In January 2026 Microsoft announced what it called a community first plan for its data centers, and on March 18, 2026 it announced that it was ending the use of nondisclosure agreements with local governments everywhere and reaching out to terminate the active ones. Brockovich's reading is that the company did not expect the backlash from the people, and corrected course before it found itself in litigation, the way PG&E did not. By April 2026 ten state legislatures had bills to restrict NDAs on data center deals, and in August the governor of Pennsylvania barred state agencies from signing them.
Primary Sources (11)
Documents, court filings, official reports, and broadcasts cited in this report.
Documented Records (7)
Chronological entries extracted from the primary sources above.
Timeline Events (3)
Dated events from this investigation in the site timeline.
More in Energy, Utilities & Data Centers
View all stories in Energy, Utilities & Data Centers → · Topic overview →
- 2026Data Center Electricity Demand, Water Consumption, and Telecom Network ControlData centers used 4.4 percent of the country's electricity in 2023, up from 1.9 percent in 2018, and could use 12 percent by 2028. The industry has negotiated through shell companies and nondisclosure agreements since Google's first data center in 2006. The government has claimed the whole telephone network for military use since 1961, and in 2011 a transit agency turned off cell service to stop a protest. Seven in ten Americans oppose a data center near them.Energy, Utilities & Data Centers
- 2022 to 2026Ohio's $1.6 Billion Data Center Tax Exemption and Soaring Grid Capacity CostsOhio's sales tax exemption for data centers cost the state $1.6 billion in 2025, almost twelve times the $136 million the Department of Taxation had forecast, and the governor paused new applications in May 2026. The price of capacity in the regional power market rose more than nine times in one auction. A group of rural Ohioans is gathering the 413,000 signatures needed to put a ban on large data centers on the 2027 ballot.Energy, Utilities & Data Centers
- 2025 to 2026Georgia Power's 1,000 Miles of New Transmission Lines and Eminent Domain for Data CentersGeorgia's largest utility plans more than 1,000 miles of new high voltage lines, up from 24 miles in its 2019 plan, to carry the 9,985 megawatts of new generation the state approved in December 2025, about 80 percent of it for data centers. The lines cross more than 330 private parcels. A homeowner who turns down the offer can have the land taken by eminent domain.Energy, Utilities & Data Centers
- December 11, 2025Executive Order 14365: Ordering the Justice Department to Sue States Over AI LawsOn December 11, 2025 the president signed Executive Order 14365, which sets up a task force at the Justice Department to sue states over their artificial intelligence laws and lets federal agencies withhold broadband money from states that keep them. Five months earlier the Senate had voted 99 to 1 to strike a ten year ban on the same laws from the budget bill.Energy, Utilities & Data Centers
- 2024 to 2026Meta's $50 Billion Louisiana Data Center: Shell Companies, $3.3 Billion in Tax Breaks, and 10 Gas PlantsThe company applied for a water permit in Richland Parish as Leley LLC, for a project called Sucre. Its sales tax exemption was approved in July 2024 without a public estimate of its value; a later estimate is $3.3 billion. In August 2025 the Public Service Commission approved three gas plants at $3.2 billion, with Meta committed for 15 years and the plants built to run for 30 or more. In July 2026 the project grew to 5 gigawatts and $50 billion, with seven more gas plants.Energy, Utilities & Data Centers