2020 to today · Energy, Utilities & Data Centers
Georgia Power's 1,000 Miles of New Transmission Lines and Eminent Domain for Data Centers
Period covered: 2025 to 2026 · 4 sources
Summary
Georgia's largest utility plans more than 1,000 miles of new high voltage lines, up from 24 miles in its 2019 plan, to carry the 9,985 megawatts of new generation the state approved in December 2025, about 80 percent of it for data centers. The lines cross more than 330 private parcels. A homeowner who turns down the offer can have the land taken by eminent domain.
The New York Times went to Georgia to film what a transmission line does to a yard. Doug, a homeowner there, lost about a quarter of his backyard the year before to a high voltage line. Nearly 400 trees were cut to make way for it. He said he and his wife had found a place they loved and within a year were told it would be changed totally. He settled with Georgia Power after more than a year of negotiating, used the money to pay down half his mortgage, and is reconsidering where to spend his retirement. There is no amount of money, he said, that could put it back the way it was.
Scale and Figures
Georgia Power is the state's largest utility, a subsidiary of Southern Company. In 2019 its ten year plan called for 24 miles of new transmission line. By 2025 the plan called for 1,065 miles. The reason is load. In 2022 the company told the Public Service Commission it expected about 400 megawatts of new large customer demand over seven years. In 2023 the estimate was 6,600 megawatts, and in 2025 it was 8,500. Most of it is data centers.
On December 19, 2025 the Public Service Commission voted unanimously to certify 9,985 megawatts of new generating capacity for Georgia Power, including five new gas units at Plants Bowen, McIntosh, and Wansley. The agreement between the commission's staff and the company says that approximately 80 percent of the new capacity is expected to power data centers. The Southern Environmental Law Center put the cost over the life of the plants at $50 billion to $60 billion and told the commission that there is not, and may never be, enough data center demand in Georgia to use that much power, and that existing customers are not adequately protected if the forecast is wrong. The commission's answer was a set of conditions: Georgia Power must financially backstop the cost through 2031 if the data center contracts do not materialize, the contracts must be submitted to the commission 30 days before they are signed, data centers must pay for their infrastructure even if they leave the state, and base rates for existing residential customers are frozen through 2028 under an order from July 31, 2025. Average residential bills had already gone up more than $43 a month in the two years before the vote.
The transmission lines to carry that power are the part of the plan that runs through people's property. Georgia Power's statewide expansion, as the Times reported it, will deliver about 10 gigawatts, enough to power twice the number of homes now in the state, with 80 percent going to data centers. A company representative in the video said the infrastructure benefits the surrounding communities and makes the grid more resilient in storms. An energy analyst in the same video said states are competing for data centers and building fast, and that the financial benefits for the state have not yet borne fruit.
What the offers look like
Rachel's family bought their house four years ago for the backyard, with room for chickens, a garden, and fruit trees. Georgia Power wants half the yard for a transmission line and offered $57,000. It is a lot of money to us, she said, and not enough to cover what the line will do to the value of the property. During the negotiations, she said, the company's representatives brought up eminent domain. A utility in Georgia has the power to take private property for a public use without the owner's consent, with the compensation set by a court if the two sides cannot agree. Georgia Power's statement is that eminent domain is a last resort it uses in less than 1 percent of its land transactions, and by mid 2026 it said it had used it five times in the past year, none on a residential home, and that its starting offer is 125 percent of appraised value.
The homeowners' answer is that the choice is not real. If the only alternative to the company's offer is a condemnation case, the offer is the outcome. One man at a church meeting of two dozen neighbors facing another line said he did not want a penny over market value, he wanted replacement value, enough to have his dream somewhere else. Another asked what stops the company from coming back in a year or two for the next line, since the data centers keep coming. A third said the property was chosen for what it offered, not for dirt and grass, and that the offers are for the dirt.
By July 2026 the plan involved more than 330 parcels along more than 1,000 miles of line. One 35 mile segment, the Ashley Park to Wansley project, crosses about 30 residential properties. A young woman posted that her childhood home was being taken by Georgia Power; the company said it had reached an agreement with her mother and did not say on what terms.
Primary Sources (4)
Documents, court filings, official reports, and broadcasts cited in this report.
Documented Records (4)
Chronological entries extracted from the primary sources above.
Timeline Events (1)
Dated events from this investigation in the site timeline.
More in Energy, Utilities & Data Centers
View all stories in Energy, Utilities & Data Centers → · Topic overview →
- 2026Data Center Electricity Demand, Water Consumption, and Telecom Network ControlData centers used 4.4 percent of the country's electricity in 2023, up from 1.9 percent in 2018, and could use 12 percent by 2028. The industry has negotiated through shell companies and nondisclosure agreements since Google's first data center in 2006. The government has claimed the whole telephone network for military use since 1961, and in 2011 a transit agency turned off cell service to stop a protest. Seven in ten Americans oppose a data center near them.Energy, Utilities & Data Centers
- 2022 to 2026Ohio's $1.6 Billion Data Center Tax Exemption and Soaring Grid Capacity CostsOhio's sales tax exemption for data centers cost the state $1.6 billion in 2025, almost twelve times the $136 million the Department of Taxation had forecast, and the governor paused new applications in May 2026. The price of capacity in the regional power market rose more than nine times in one auction. A group of rural Ohioans is gathering the 413,000 signatures needed to put a ban on large data centers on the 2027 ballot.Energy, Utilities & Data Centers
- 2006 to 2026How Cities and Counties Sign Secret NDAs Before Approving Data CentersErin Brockovich put up a map where people could report a data center near them and got 3,862 reports in a month from 49 states. The reports said the same thing: nobody was told, the officials had signed nondisclosure agreements, and the announcement was the construction. Elected officials in Louisiana have signed at least 54 NDAs since 2024. Microsoft ended its use of NDAs with local governments in March 2026.Energy, Utilities & Data Centers
- December 11, 2025Executive Order 14365: Ordering the Justice Department to Sue States Over AI LawsOn December 11, 2025 the president signed Executive Order 14365, which sets up a task force at the Justice Department to sue states over their artificial intelligence laws and lets federal agencies withhold broadband money from states that keep them. Five months earlier the Senate had voted 99 to 1 to strike a ten year ban on the same laws from the budget bill.Energy, Utilities & Data Centers
- 2024 to 2026Meta's $50 Billion Louisiana Data Center: Shell Companies, $3.3 Billion in Tax Breaks, and 10 Gas PlantsThe company applied for a water permit in Richland Parish as Leley LLC, for a project called Sucre. Its sales tax exemption was approved in July 2024 without a public estimate of its value; a later estimate is $3.3 billion. In August 2025 the Public Service Commission approved three gas plants at $3.2 billion, with Meta committed for 15 years and the plants built to run for 30 or more. In July 2026 the project grew to 5 gigawatts and $50 billion, with seven more gas plants.Energy, Utilities & Data Centers