2020 to today · Energy, Utilities & Data Centers

Georgia Power's 1,000 Miles of New Transmission Lines and Eminent Domain for Data Centers

Period covered: 2025 to 2026 · 4 sources

Summary

Georgia's largest utility plans more than 1,000 miles of new high voltage lines, up from 24 miles in its 2019 plan, to carry the 9,985 megawatts of new generation the state approved in December 2025, about 80 percent of it for data centers. The lines cross more than 330 private parcels. A homeowner who turns down the offer can have the land taken by eminent domain.

The New York Times went to Georgia to film what a transmission line does to a yard. Doug, a homeowner there, lost about a quarter of his backyard the year before to a high voltage line. Nearly 400 trees were cut to make way for it. He said he and his wife had found a place they loved and within a year were told it would be changed totally. He settled with Georgia Power after more than a year of negotiating, used the money to pay down half his mortgage, and is reconsidering where to spend his retirement. There is no amount of money, he said, that could put it back the way it was.

Scale and Figures

Georgia Power is the state's largest utility, a subsidiary of Southern Company. In 2019 its ten year plan called for 24 miles of new transmission line. By 2025 the plan called for 1,065 miles. The reason is load. In 2022 the company told the Public Service Commission it expected about 400 megawatts of new large customer demand over seven years. In 2023 the estimate was 6,600 megawatts, and in 2025 it was 8,500. Most of it is data centers.

On December 19, 2025 the Public Service Commission voted unanimously to certify 9,985 megawatts of new generating capacity for Georgia Power, including five new gas units at Plants Bowen, McIntosh, and Wansley. The agreement between the commission's staff and the company says that approximately 80 percent of the new capacity is expected to power data centers. The Southern Environmental Law Center put the cost over the life of the plants at $50 billion to $60 billion and told the commission that there is not, and may never be, enough data center demand in Georgia to use that much power, and that existing customers are not adequately protected if the forecast is wrong. The commission's answer was a set of conditions: Georgia Power must financially backstop the cost through 2031 if the data center contracts do not materialize, the contracts must be submitted to the commission 30 days before they are signed, data centers must pay for their infrastructure even if they leave the state, and base rates for existing residential customers are frozen through 2028 under an order from July 31, 2025. Average residential bills had already gone up more than $43 a month in the two years before the vote.

The transmission lines to carry that power are the part of the plan that runs through people's property. Georgia Power's statewide expansion, as the Times reported it, will deliver about 10 gigawatts, enough to power twice the number of homes now in the state, with 80 percent going to data centers. A company representative in the video said the infrastructure benefits the surrounding communities and makes the grid more resilient in storms. An energy analyst in the same video said states are competing for data centers and building fast, and that the financial benefits for the state have not yet borne fruit.

What the offers look like

Rachel's family bought their house four years ago for the backyard, with room for chickens, a garden, and fruit trees. Georgia Power wants half the yard for a transmission line and offered $57,000. It is a lot of money to us, she said, and not enough to cover what the line will do to the value of the property. During the negotiations, she said, the company's representatives brought up eminent domain. A utility in Georgia has the power to take private property for a public use without the owner's consent, with the compensation set by a court if the two sides cannot agree. Georgia Power's statement is that eminent domain is a last resort it uses in less than 1 percent of its land transactions, and by mid 2026 it said it had used it five times in the past year, none on a residential home, and that its starting offer is 125 percent of appraised value.

The homeowners' answer is that the choice is not real. If the only alternative to the company's offer is a condemnation case, the offer is the outcome. One man at a church meeting of two dozen neighbors facing another line said he did not want a penny over market value, he wanted replacement value, enough to have his dream somewhere else. Another asked what stops the company from coming back in a year or two for the next line, since the data centers keep coming. A third said the property was chosen for what it offered, not for dirt and grass, and that the offers are for the dirt.

By July 2026 the plan involved more than 330 parcels along more than 1,000 miles of line. One 35 mile segment, the Ashley Park to Wansley project, crosses about 30 residential properties. A young woman posted that her childhood home was being taken by Georgia Power; the company said it had reached an agreement with her mother and did not say on what terms.

← 2020 to today

Primary Sources (4)

Documents, court filings, official reports, and broadcasts cited in this report.

The New York Times. Homeowners in Georgia whose yards are crossed by new Georgia Power transmission lines, and the company's response.
2025
Southern Environmental Law Center. The December 19, 2025 vote, the five gas units, and the $50 billion to $60 billion lifetime cost estimate.
2026
Georgia Public Service Commission. Load forecasts from 400 to 8,500 megawatts, the 9,985 megawatt certification, the January 2025 large load rules, and the rate freeze.
2026
Fortune. More than 330 parcels, the 35 mile Ashley Park to Wansley line, and Georgia Power's statements on eminent domain.

Documented Records (4)

Chronological entries extracted from the primary sources above.

2025
2022 to 2025
Georgia Power's forecast of new large customer load went from about 400 megawatts over seven years, in 2022, to 6,600 megawatts in 2023 and 8,500 megawatts in 2025, most of it data centers. In January 2025 the commission adopted rules requiring large load customers to accept minimum bills and longer contracts and to pay for new infrastructure even if they leave the state, and on July 31, 2025 it froze Georgia Power's base rates for existing residential customers through 2028.
Georgia Public Service Commission. Violates: None in law. Listed for the forecast the transmission plan rests on.. Source: Data Center Fact Sheet, Georgia Public Service Commission
December 19, 2025
The Georgia Public Service Commission voted unanimously to certify 9,985 megawatts of new generating capacity for Georgia Power, including five new gas units at Plants Bowen, McIntosh, and Wansley. The agreement says approximately 80 percent of the capacity is expected to power data centers. The Southern Environmental Law Center estimated the lifetime cost at $50 billion to $60 billion and told the commission that existing customers' bills are not adequately protected if the data center demand does not appear.
“There currently is not, and may never be, data center customers that need this much energy from Georgia Power.”
Georgia Public Service Commission; Georgia Power. Violates: None in law. Listed for scale and for who the capacity is for.. Source: PSC unanimously votes to approve Georgia Power's data center plan without sufficient customer protections, Southern Environmental Law Center
2026
2019 to 2026
Georgia Power's 2019 ten year plan called for 24 miles of new transmission line. By 2025 the plan called for 1,065 miles, to deliver about 10 gigawatts, 80 percent of it to data centers. One homeowner lost a quarter of his backyard and nearly 400 trees to a line; another was offered $57,000 for half of hers and said the company's representatives raised eminent domain during the negotiations. Georgia Power's statement is that eminent domain is a last resort it uses less than 1 percent of the time.
“It feels like the only option is to reach a settlement with them. And I don't really see what leverage the average person has in that situation.”
Georgia Power. Violates: Fifth Amendment. Private property taken for a public use, with the lines serving private companies that will use 80 percent of the power, at prices set under the threat of condemnation.. Source: When the Power Company Takes Your Land for a Data Center, The New York Times
July 26, 2026
Georgia Power's transmission expansion of more than 1,000 miles crosses more than 330 private parcels. One 35 mile segment, the Ashley Park to Wansley line, affects about 30 residential properties. The company said it had used eminent domain five times in the past year, none on a residential home, and that its starting offer is 125 percent of appraised value.
“My childhood home is being taken by Georgia Power.”
Georgia Power. Violates: Fifth Amendment. Listed for the count of properties.. Source: Eminent domain for data centers targets properties across a 1,000-mile grid expansion, Fortune

Timeline Events (1)

Dated events from this investigation in the site timeline.

December 19, 2025
Georgia certifies 9,985 megawatts of new generation, 80 percent for data centers
Unanimous vote. Five new gas units, and more than 1,000 miles of transmission line to carry it.
Georgia Power's 1,000 Miles of New Transmission Lines and Eminent Domain for Data Centers | Spirit of '76