2020 to today · Energy, Utilities & Data Centers

Ohio's $1.6 Billion Data Center Tax Exemption and Soaring Grid Capacity Costs

Period covered: 2022 to 2026 · 7 sources

Summary

Ohio's sales tax exemption for data centers cost the state $1.6 billion in 2025, almost twelve times the $136 million the Department of Taxation had forecast, and the governor paused new applications in May 2026. The price of capacity in the regional power market rose more than nine times in one auction. A group of rural Ohioans is gathering the 413,000 signatures needed to put a ban on large data centers on the 2027 ballot.

Jason Ferrier, who posts as the Ohio Housing Nerd, grew up a few miles from New Albany, outside Columbus. The farmland he explored as a child is now the New Albany International Business Park, the center of Ohio's data center corridor. His video counts 226 data centers in the state and 280 expected by 2030, and its argument is that the buildout is a transfer of land and public money to a few companies, paid for on every Ohioan's electric bill.

The bills

The video's central claim is that electric capacity prices in Ohio went up nine times in one year. The record supports it. Ohio is part of PJM, the regional market that buys generating capacity for 13 states and Washington. In the auction held in July 2024 for the 2025 to 2026 delivery year, the price cleared at $269.92 per megawatt day, against $28.92 the year before, and the total cost went from $2.2 billion to $14.7 billion. The market's independent monitor attributed $9.3 billion of that to data center load, which is where the video's figure that data centers drove 63 percent of the increase comes from. The next auction cleared at its cap, $329.17, for a total of $16.1 billion, and the one after that at $333.44 and $16.4 billion. Capacity costs are a share of the supply charge on a household bill; the video puts the 2025 increase in Ohio bills at 10 to 35 percent.

In July 2025 the Public Utilities Commission of Ohio approved a tariff for AEP Ohio, the utility that serves the corridor, requiring data centers over 25 megawatts to pay for at least 85 percent of the capacity they sign up for, for up to 12 years, whether they use it or not, with exit fees if a project is cancelled. The Data Center Coalition, the industry's trade group, called it a stark departure from what other states had done.

The tax breaks

Ohio exempts data centers from the state's 5.75 percent sales tax on equipment. In 2024 the exemption cost the state $555 million and local governments another $166.8 million. In 2025 it cost the state $1.6 billion. The Department of Taxation's forecast had been $136 million. On May 27, 2026 Governor DeWine suspended new applications while a legislative committee studies the industry. His announcement said the companies already holding exemptions had reported $27.2 billion in capital investment in 2025 and that the pause is not a data center ban. The existing agreements continue, and property tax abatements granted by local governments were not touched. The video's figures are that Ohio and the federal government have put an estimated $14 billion into the corridor, that the 2025 exemption was 11 times the state's projection, and that Google, Meta, and Amazon each locked in about $600 million in exemptions. The first two match the record; the per company figures are the video's.

The video also counts Intel. By its account Ohio put $600 million into Intel's New Albany plant and the federal government $1.5 billion through the CHIPS Act. On August 22, 2025 the federal government bought 433.3 million shares of Intel, a 9.9 percent stake, for $8.9 billion, using $5.7 billion in CHIPS Act grants that had been awarded but not paid and $3.2 billion from a Defense Department program. The government agreed to vote with Intel's board and takes no seat on it. The video's point is that the taxpayers now own a tenth of the company without having been asked, and that the federal government is at the same time the industry's largest customer, spending about $75 billion a year on information technology.

The land

Ferrier tracked the purchases. Les Wexner's New Albany Company, the master developer of the business park, built the corridor to attract data centers, sold land to Intel, Amazon, and Microsoft, and, by his count, walked away with nearly $300 million while still holding more than $1 billion of land in central Ohio. Meta's campus was bought under an LLC called Side Cat. Google's was bought under one called Montauk. QTS, the largest independent data center operator, is owned by Blackstone, the firm that bought tens of thousands of single family homes after 2012. His figures for the area are land at $25,000 an acre before and $365,000 an acre now, and a typical house at $150,000 in 2012 and $419,000 today. He says the facilities need about 5 million gallons of water a day each for evaporative cooling, that the grid cannot connect new ones fast enough, and that a developer has proposed a 430 megawatt gas plant in New Albany to run them directly.

What Ohioans are doing

At least 18 communities have passed moratoriums or zoning changes, by the video's count: Jackson Township a unanimous 12 month moratorium, Washington Township a 360 day moratorium before any application, and South Bloomfield the removal of its industrial zone entirely. A group called Conserve Ohio, organized by farmers and residents of Adams and Brown counties who watched their neighbors' land bought through shell companies, is circulating a constitutional amendment that would prohibit data centers with a peak load over 25 megawatts. The Ohio Ballot Board approved the petition language in April 2026. They needed 413,000 valid signatures from at least 44 of the state's 88 counties by July 1, 2026 to make the November ballot and had about 70,000 by mid June, so the target is now 2027. The signatures already gathered remain valid. Ferrier interviewed one of the organizers, Jessica Baker, and links the petition.

← 2020 to today

Primary Sources (7)

Documents, court filings, official reports, and broadcasts cited in this report.

Ohio Housing Nerd. Jason Ferrier on the New Albany corridor: the shell companies, the tax exemptions, the capacity prices, and the ballot effort.
2025
Utility Dive. The PUCO order: 85 percent minimum charges for up to 12 years for data centers over 25 megawatts.
2025
Intel Corporation. 433.3 million shares at $20.47, a 9.9 percent stake, paid with $5.7 billion in CHIPS grants and $3.2 billion from the Secure Enclave program.
2025
PJM Interconnection. Cleared at the $333.44 cap, $16.4 billion total, 6,517 megawatts short of the reliability requirement. Includes the prior auctions' prices and totals: $14.7 billion for 2025/2026 and $16.1 billion for 2026/2027.
2026
Signal Ohio. $1.6 billion in 2025 against a $136 million forecast; $555 million in 2024 plus $166.8 million local.
2026
Office of the Governor of Ohio. New applications suspended while the legislature's committee studies the industry.
2026
Ohio Capital Journal. Conserve Ohio's amendment, the 25 megawatt threshold, and the signature count.

Documented Records (6)

Chronological entries extracted from the primary sources above.

2025
July 2025
The Public Utilities Commission of Ohio approved a tariff for AEP Ohio requiring data centers over 25 megawatts to pay at least 85 percent of their contracted capacity each month for up to 12 years, including a four year ramp, with exit fees if a project is cancelled. The Data Center Coalition called it a stark departure from the solutions enacted in other states.
Public Utilities Commission of Ohio. Violates: None in law. Listed as one of the first rules to put the cost of the buildout on the customers who cause it.. Source: Ohio regulators approve AEP data center interconnection rules, Utility Dive
August 22, 2025
The federal government bought 433.3 million shares of Intel at $20.47 a share, a 9.9 percent stake, for $8.9 billion, paid with $5.7 billion in CHIPS Act grants that had been awarded but not yet paid and $3.2 billion from the Secure Enclave program. The government takes no board seat and agreed to vote with Intel's board on matters requiring shareholder approval. Congress did not vote on the purchase.
“The government's investment in Intel will be a passive ownership, with no Board representation or other governance or information rights.”
United States Department of Commerce; Intel Corporation. Violates: Article I. Money appropriated as grants for factories was used to buy stock in the company.. Source: Intel and Trump Administration Reach Historic Agreement to Accelerate American Technology and Manufacturing Leadership, Intel Corporation
December 17, 2025
PJM's auction for the 2027 to 2028 delivery year cleared at the new cap of $333.44 per megawatt day, cost $16.4 billion, and procured 6,517 megawatts less than the reliability requirement, a 14.4 percent reserve margin against a 20 percent target. The requirement had risen by 5,250 megawatts in a year, which PJM attributed largely to additional large loads.
PJM Interconnection. Violates: None in law. Listed for the number and the shortfall.. Source: 2027/2028 Base Residual Auction Report, PJM Interconnection
2026
2024 to 2025
Ohio's sales tax exemption for data center equipment cost the state $555 million in 2024, plus $166.8 million in local sales tax, and $1.6 billion in 2025. The Ohio Department of Taxation's forecast had been $136 million. On May 27, 2026 Governor DeWine suspended new applications while a legislative committee studies the industry, leaving existing agreements and local property tax abatements in place.
State of Ohio; Governor Mike DeWine. Violates: None in law. Listed because the cost was almost twelve times what the state forecast.. Source: DeWine abruptly pauses a major tax break for data centers in Ohio, Signal Ohio
2022 to 2026
The Ohio Housing Nerd's account of the New Albany corridor: 226 data centers in Ohio with 280 expected by 2030; Meta's campus bought under an LLC called Side Cat and Google's under one called Montauk; QTS owned by Blackstone; land at $25,000 an acre before and $365,000 an acre now; a typical house at $150,000 in 2012 and $419,000 today; Ohio and the federal government putting an estimated $14 billion into the corridor; and at least 18 communities passing moratoriums or zoning changes.
“They got the land, they got the tax breaks, but ask yourself, what did Ohio get in return?”
Jason Ferrier, Ohio Housing Nerd. Violates: None in law. The figures are the video's; the tax exemption cost and the capacity prices are confirmed by the state's numbers and PJM's.. Source: I Tracked Ohio's Data Center Land Grab. Here's What I Found, Ohio Housing Nerd
April to June 2026
Conserve Ohio, a group organized by farmers and residents of Adams and Brown counties, is circulating a constitutional amendment to prohibit data centers with a peak load over 25 megawatts. The Ohio Ballot Board approved the petition in April 2026. The group needed 413,000 valid signatures from at least 44 counties by July 1, 2026 and had about 70,000 by June 18, so the target is now the 2027 ballot. The signatures remain valid.
“We want to make it clear: we will not be stopping. Construction won't be stopping, so signature gathering and community action will not be stopping.”
Conserve Ohio. Violates: None in law. Listed as the record of the petition.. Source: Ohio proposed constitutional amendment to ban data centers will not be on this year's ballot, Ohio Capital Journal

Timeline Events (3)

Dated events from this investigation in the site timeline.

May 27, 2026
Ohio pauses its data center tax exemption
The exemption had cost $1.6 billion in 2025 against a $136 million forecast. Existing agreements continue.
August 22, 2025
Federal government takes a 9.9 percent stake in Intel
$8.9 billion paid with CHIPS grants and a Defense Department program, with no vote in Congress.
July 2025
Ohio regulators make data centers pay for 85 percent of what they reserve
AEP Ohio's tariff for customers over 25 megawatts, for up to 12 years, with exit fees.